Inspections Required
The permit holder is
responsible for calling the Building Department when each inspection phase is
ready. Do not proceed with work until the inspections are completed and
approved.
Types of Inspections Required
Temporary Electrical Service (If Applicable) - permit must be posted
Footer (must conform to section 1804 of the Florida Building Codes) - trenches clean and clear of debris, steel in place (vertical supports if required), any forms in place, all vegetation and organic material shall be removed from the floor area, toilet facilities for workers (Sec. 311 Florida Plumbing Code), notice of commencement posted on permit board.
Underslab - plumbing rough-in (pressure test on all water lines, sewer requirement of 5' of head, Hard sleeves through foundation wall, 032 soft sleeve through floor), any electrical conduit, Air conditioning chase if applicable.
Floor Slab - wire and steel in place, vapor barrier, soil treatment (sticker to be posted on permit board) and forming complete.
Concrete Block Building - tie beam ready to pour, all steel in place and all forms in place and properly braced. Ladder required to be on site.
Roofing and Siding Nail Off (ladder required to be on site).
Dry-in - framing complete (nothing covered up, no insulation installed), windows set, plumbing top out, mechanical and electrical rough-in complete. Electrical must be with panel set (breakers do not need to be installed). If using brick, brick ties will be inspected.
Insulation
Sheet Rock Nailing
Temporary Permanent Power - by Building Inspector's approval and power in builder's name only for a period of no more than 15 days prior to certificate of occupancy. 911 address must be posted.
Final / Certificate of Occupancy - building complete, all trim, paint, etc.; plumbing complete (fixtures set); electrical complete (fixtures set, panel complete with breakers installed); mechanical complete, ready for start up; copy of final/final on Septic Tank must be completed and a copy on file before Final Inspection; certificate of final termite treatment. Everything complete, ready to move in, nothing in building except for major appliances and floor covering. Do not request a Final CO inspection unless you have everything covered herein completed. After completion of the final inspection, you will receive a Certificate of Occupancy (CO) that can be picked up at the Building Department office between the hours of 7:30 am and 4:00 pm. The CO is issued only after the authorization of the Inspector.
A building or structure may not be occupied and a municipality, political subdivision, or any state or federal agency may not authorize occupancy until the department approves the final installation of the onsite sewage treatment and disposal system. FS 381.0065(4)
The building may not be occupied until the Building Official has issued the Certificate of Occupancy. (Florida Building Code 106.1)
To make inspection appointments please contact the Building Department at 850-482-9802. These appointments must be made at least the day before inspection is desired. Make sure you have the permit number prior to making inspection requests.
Reinspection
Any inspection requests
called in and not ready when inspector gets to site or those that fail initial
inspection will require reinspection. A reinspection fee of $20.00 will be
charged on all such inspections. Fee must be paid prior
to a reinspection being made. Reinspection requests will be handled in the
same manner as the initial inspection request, with the exception that you will
be identify it as a reinspection.
Jackson County Building
Department
4487 Lafayette Street
Marianna, FL 32448
Phone: (850) 482-9805
FAX: (850) 718-0029
COUNTY HOME | LIVING HERE | DOING BUSINESS HERE | WORKING HERE | VISITING | GOVERNMENT | EMERGENCIES | CONTACT US | STATE OF FLORIDA WEBSITE

©
2004
Jackson County Florida,
Selected information in this website requires
Adobe® Acrobat® Reader™,